South Texas Chapter AGC Project Summary

Currently Available in AGC Planroom:

 Corpus – Del Mar College Music Building Additions & Renovations, 6-27-12, 2:00 pm

Corpus – Fire Station No. 5 Relocation, 6-27-12, 2:00 pm

Corpus – Evelyn Price Park Improvements, 6-27-12, 2:00 pm

Corpus – Charles Drive Improvements, Leopard St. to Maple Leaf Dr., 6-27-12, 2:00 pm

Corpus – St. John Vianney – Residence for Priest, 6-27-12, 2:00 pm

Corpus – Maintenance Painting at the Bulk Terminal, 6-29-12, 2:30 pm

Corpus – Replacement of Conveyor Belts on CB-5, CB-7, CB-8, CB-9 and Shiploader at Bulk Dock 2, 6-29-12, 3:00 pm

Corpus – Upgrades to the Mother Teresa Shelter, 7-3-12, 2:00 pm

Port Lavaca – 2010, 2011, 2012 CFP Renovations, 7-3-12, 11:00 am

Pawnee – ISD Covered Play Area, 7-10-12, 3:00 pm

Corpus – Re-Roofing of Haas Middle School and Smith Elementary School, 7-11-12, 10:30 am

San Benito – 2012 Odem Road Bridge Force Main Repairs, 7-11-12, 2:00 pm

Gregory – Edna Lift Station, Forcemain, and Water Treatment Plant Improvements Project – Phase II, 7-12-12, 2:00 pm

Corpus – CCISD Time & Material – Powerwashing Services, 7-13-12, 11:00 am

McAllen – TXDPS Regional Office Renovations, 7-19-12, 3:00 pm

Rio Grande City – TXDPS Area Office, 7-19-12, 3:00 pm

 

CORPUS – DEL MAR COLLEGE MUSIC BUILDING ADDITIONS & RENOVATIONS  New bid date
Addendum 1, 2 (
This addendum is 150 pages.  I will be happy to email it to you.   Bid date remains the same, but the time for delivery changes (noted on first page).
CDC ID Number:         X051400178
AGC Bin Number:      7
Bid Date/Time:           6-27-12, 2:00 pm
Est. Cost:
Scope:                         This project includes all work associated with the complete and fully finished Music Building addition including all adjacent and related exterior site, civil and landscaping improvements and the complete demolition of the adjacent Stone Writing Center structure.  The scope of this project also includes but is not limited to the following disciplines and trades:  Drilled pier and suspended slab foundations, steel and concrete load bearing structural systems, CMU and drywall exterior envelop backup, full vapor barrier (Dampproofing) envelop backup, modified asphalt roofing system, modular face brick, structural glazed tile, and cast stone veneer assemblies, curtain wall and metal panel assemblies complete the t=exterior finishes.  Interior finish out includes, elevator and stair systems, drywall an CMU partitions, drywall, acoustic panel, and metal ceiling assemblies and soffits, custom wood wall and ceiling panels, audio/visual systems, commissioned mechanical, electrical and plumbing systems, built in place millwork and selected equipment and systems.
Notes:                         Pre-Proposal Conference:  5-31-12, 10:00 am, Del Mar Purchasing Dept. Conference Room
Owner:                        Del Mar College District
Arch/Eng:                   WKMC Architects, Inc., Corpus 361/887-6696
Richter Architects, Corpus
General Contractors:   All AGC members (listed in bold face and capital letters) invite all SBE/MBE/WBE/HUB firms to submit sub-bids and material quotations on this project.
                           *AGC BEECROFT CONST., Corpus  361/882-6791, 361/882-6392
Drymalla Const., 979/732-5731, 979/732-3663
Teal Const., 361/882-4825, 361/882-4630
Journeyman Const., 361/299-1001, 361/299-1002


CORPUS – FIRE STATION NO. 5 RELOCATION
ADDENDUM 1
CDC ID Number:             U092800595                               �
AGC Bin Number:            2
Bid Date/Time:             6-27-12, 2:00 pm
Est. Cost:                 $1,750,709
Scope:                     Project consists of the demolition of a two-story building, and the construction of a single story fire station and a separate joint use building.  Site improvements consist of existing paving demolition and new concret paving drives and parking area, limited curb and gutter reconstruction, new site utilities, off-site utility tie-ins and street work, and lawn areas.  Building construction consists of tilt-up concrete wall panels, steel framed roof system, drilled pier and suspended floor system, storefront openings, drywall partitions, flooring, suspended ceiling systems, hollow metal and plastic laminate doors, millwork, and HVAC, plumbing, fire sprinkler and electrical systems, in accordance with the plans, specifications and contract documents.
Notes:                     Pre-bid meeting 6-13-12, 10:00 am, CC Engr. Dept.
Owner:                     City of Corpus Christi
Arch/Eng:                  Solka Nava Torno
General Contractors:

The DLP Group, 361/857-5050, 361/857-1122
South Plains Contracting, 361/355-2860, 361/221-1362
Barcom Commercial, 361/851-1000, 361/851-1717
Safenet Services, 361/93-9300, 361/37-8853
Elite General Contr., 361/765-7080, 361/980-0865
Sal-con Inc., 361/853-3755, 361/853-1338
Fox Tree & Landscape, 361/992-6928, 361/991-7841
Moerbe Insulation Corp., 361/584-3501, 361/584-5114
Corbet Group, Dallas 214/905-0585, 214/905-0589
TBC Commercial Const., San Antonio 210/402-0008, , 210/402-0099
Journeyman Const., Austin 361/299-1001, 361/299-1002
Maltby Builders, Kingsville 361/592-8426, 361/592-8447
Rusty Van Fleet Const., Kingsville 361/516-1034, 361/516-1035
JTB Services, Houston, 713/941-4141
Machinery & Materials, Inc., Corpus 361/765-1737
CORPUS – EVELYN PRICE PARK IMPROVEMENTS

CDC ID Number:             X061100191       �
AGC Bin Number:        8
Bid Date/Time:             6-27-12, 2:00 PM
Est. Cost:                 $140,470
Scope:                     Consisting of the rehabilitation of portions of the existing parking lot, sidewalks, and drainage ditches at Evelyn Price Park.  Includes the removal and replacement of approximately 2,221 square yards of HMAC parking area, associated, ADA compliant pedestrian infrastructure, and installation of drainage culverts.
Notes:                     Pre-bid meeting: 6-20-12, 10:00 am, Dept. of Engr. Services
Owner:                     City of Corpus Christi
Arch/Eng:                  RVE, Inc.
General Contractors:
Garrett Const., Ingleside 361/776-7575, 361/776-3993
GT Development & Contr., Cotulla 228-762-9899, 228/762-9815
Barcom Commercial, Corpus 361/851-1000, 361/851-1717

 

CORPUS – CHARLES DRIVE IMPROVEMENTS, LEOPARD STREET TO MAPLE LEAF DRIVE
Addendum 1
CDC ID Number:             V062900520
AGC Bin Number:        9
Bid Date/Time:             6-27-12, 2:00 PM
Est. Cost:                 1,183,473
Scope:                     This project consists of reconstruction of approximately 600 lineal feet of street improvements which will include demolition, excavation, subgrade treatment, flexible base, pavement, concrete curb and gutter and sidewalk; replacement of existing water distribution system with 8 inch C-900 PVC and related individual services; replacement of approximately 600 lineal feet of 8 inch PVC wastewater line with related individual service connections; approximately 400 feet of single course surface treatment and 4,000 feet of offsite stormwater improvements with related manholes and other appurtenances, and other work required to complete the project.
Notes:                     Pre-bid meeting: 6-20-12, 10:00 am, Engr. Services Conf. Rm.
Owner:                     City of Corpus Christi
Arch/Eng:                   Corpus Christi Dept. of Engineering Services
General Contractors:
Garrett Const., Ingleside 361/776-7575, 361/776-3993
GT Development & Contr., Cotulla 228/762-9899, 228-762-9815
Bay LTD, Corpus 361/299-3729, 361/289-2304
Hanson Pipe & Precast, Robstown 361/767-1060, 361/387-9071

 

CORPUS – ST. JOHN VIANNEY – RESIDENCE FOR PRIESTS
Addendum 1, 2, 3, 4

CDC ID Number:             X061500637           �
AGC Bin Number:          10
Bid Date/Time:             6-27-12, 2:00 pm
Est. Cost:
Scope:                     The St. John Vianney Residence for Priest is a multi-building development and site work located in Corpus Christi, Tx.  The specific project involves site utility infrastructure, building pads with paving and sidewalks, construction of Community building, Gatekeeper residence, Medical residence, and approximately 8 Duplex living units.  Work includes civil, structural, mechanical, electrical, and plumbing infrastructure to support new construction.�
Notes:                     Pre-Bid 6-13-12
Owner:                     The Diocese of Corpus Christi
Arch/Eng:                  CLK Architects & Assocites
General Contractors:       All AGC members (listed in bold face and capital letters) invite all SBE/MBE/WBE/HUB firms to submit sub-bids and material quotations on this project.
AGC MARSHALL COMPANY,  Corpus 361/883-4369
AGC EWING CONST., Corpus 361/882-6525
Barcom Commercial, Coropus 361/851-1000
Stewart Builders, Georgetown 512/763-8900

 

 

CORPUS – MAINTENANCE PAINTING AT THE BULK TERMINAL

CDC ID Number:
AGC Bin Number:       13
Bid Date/Time:            6-29-12, 2:30 pm
Scope:                     Work consists of sandblasting and paintng of bulk material handling equipment throughout the Bulk Terminal complex and in the paint building as directed by the Bulk Terminal forman.
Notes:                     Mandatory pre-bid conference: 6-25-12, 2:30 pm, PCCA Bulk Terminal at 4820 Navigation Blvd., Corpus Christi
Owner:                     Port of Corpus Christi Authority
Arch/Eng:
General Contractors:

 

CORPUS – REPLACEMENT OF CONVEYOR BELTS ON CB-5, CB-7, CB-8, CB-9 AND SHIPLOADER AT BULK DOCK 2

CDC ID Number:              X061500069          �
AGC Bin Number:         14
Bid Date/Time:             6-29-12, 3:00 pm
Scope:                    The work consists of removing existing conveyor belts and furnishing and installing new conveyor belts on conveyors CB-5, CB-7, CB-8, CB-9 and the Shiploder at Bulk Dock 2
Notes:                     Pre-bid conference 6-25-12, 1:30 pm, CCA Bulk Terminal at 4820 Navigation Blvd., Corpus Christi
Owner:                  Port of Corpus Christi Authority
Arch/Eng:
General Contractors:

 

CORPUS – UPGRADES TO THE MOTHER TERESA SHELTER

CDC ID Number:             X062500813
AGC Bin Number:
Bid Date/Time:             7-3-12, 2:00 pm
Scope:                     Upgrades to the existing Kitchen / Dining area and to the Main Office / Entry area.  Modifications are generally interior, with minor ancillary exterior work.
Notes:                     Pre-bid Conference:  6-26-12, 10:00 am
Owner:                     Mother Teresa Shelter, Inc.
Arch/Eng:                  Ferrell/Brown & Associates, 361/854-1967
General Contractors:

 

PORT LAVACA – 2010,2011-2012 CFP RENOVATIONS
Addendum 1, 2

CDC ID Number:         �
AGC Bin Number:            20
Bid Date/Time:             7-3-12, 11:00 AM
Scope:                     The project involves the labor, material, supervision, equipment tools, and all the incidentals required for cast-in-place drilled concrete stabilization piers, concrete sidewlk demolition and construction, concrete pavement demolition and construction and site grading renovations and other related work.
Notes:                     Pre-bid meeting 6-21-12, 10:30 am
Owner:                     Port Lavaca Housing Authority        �
Arch/Eng:                  Alpha Engineering, Kingsville 361/592-2977
General Contractors:

 

PAWNEE – ISD COVERED PLAY AREA

CDC ID Number:          X062500603   �
AGC Bin Number:
Bid Date/Time:             7-10-12, 3:00 pm
Scope:                     Construction of the Pawnee Elementary / Junior High School Covered Play Area .
Notes:
Owner:                     Pawnee Independent School District
Arch/Eng:                  Lamarr Womack & Associates, 361/884-7442
General Contractors:

 

CORPUS – RE-ROOFING OF HAAS MIDDLE SCHOOL AND SMITH ELEMENTARY SCHOOL

CDC ID Number:            X051400921
AGC Bin Number:          15
Bid Date/Time:             7-11,12, 10:30 am
Scope:                     The work includes roof system removal and replacement and overlay as indicated for Haas Middle School and Smith Elementay School.  At designated locations, remove roof system and flashings down to roof deck, repair deck as needed, and provide new insulation and a SBS Modified Roof Membrane System.  At designated locations, overlay the existing roof sytem with new lightweight insulating concrete and a new SBS Modified Roof membrane System.
Notes:                     Pre-proposal conference:  6-14-11:00 am
Owner:                     Corpus Christi Independent School District
Arch/Eng:                  Amtech Building Sciences, Inc., McAllen 956/686-3095
General Contractors:

 

SAN BENITO – 2012 ODEM ROAD BRIDGE FORCE MAIN REPAIRS
Addendum 1 with bid date change
CDC ID Number
:
AGC Bin Number:        16
Bid Date/Time:             7-11-12,  2:00 pm
Scope:                     The project consists of a new 16-inch Force main, and All Related Appurtenances to be Connected to an Existing 12-inch Force Main Allowing the Removal of a Portion of Existing 12-inch Force Main Temporarily Resting on Top of the Bridge.  The Proposed Force Main Shall be placed on the North Side of the Bridge, Under the Existing Drainage Ditch.
Notes:                     Pre-bid Meeting 6-21-12, 2:00 pm 400 N. Travis St., San Bentio
Owner:                     The City of San Benito
Arch/Eng:                   Coym, Rehmet & Gutierrez Engineering, Corpus 361/991-8550
General Contractors:

 

GREGORY – EDNA LIFT STATION, FORCEMAIN, AND WATER TREATMENT PLANT IMPROVEMENTS PROJECT – PHASE II
Addendum 1 with bid date change

CDC ID Number:
AGC Bin Number:
Bid Date/Time:             7-12-12, 2:00 pm
Scope:                     Water system improvements consist of the installation of a new 400,000 gallon galvanized water storage tank and booster pump station for the New TPCO Facility in Gregory, San Patricio County, Tx as per the contract documens, specifications, and plans.
Notes:                     Pre-bid conference:  6-22-12, 10:00 am, Gregory City Hall
Owner:                     The City of Gregory
Arch/Eng:                  LNV, Corpus  361/883-1984
General Contractors:

CORPUS – CCISD TIME & MATERIAL – POWERWASHING SERVICES

CDC ID Number:
AGC Bin Number:        46
Bid Date/Time:             7-13-12, 11:00 am           �
Scope:                     This is a twelve (12) month award with an option to extend for four (4) additional twelve (12) month periods subject to approval by both parties.  The initial period begins upon award and ends May 30, 2013
Owner:                     Corpus Christi Independent School District
Arch/Eng:                   CCISD Office of Purchasing & Disribution
General Contractors:

 

MCALLEN – TXDPS REGIONAL OFFICE RENOVATIONS
Addendum:  1 bid date

CDC ID Number:          X062000252
AGC Bin Number:
Bid Date/Time:            7-19-12, 3:00 PM
Scope:                           The work consists primarily of but is not necesarily limited to the following description as described and designated in the Contract Documents:  Asbestos Abatement, Interior Demolition, interior remodeling, reroofing, new canopy and site improvements.
Notes:
Owner:                         Texas Facilities Commission, Austin
Arch/Eng:                   Rike Ogden Figueroa Allex Architects, McAllem 956/686-7771
General Contractors:

 

RIO GRANDE CITY – TXDPS AREA OFFICE�
ADDENDUM  1 bid date

CDC ID Number:              X062000252  �
AGC Bin Number:
Bid Date/Time:                  7-19-12, 3:00 pm
Scope:                              The work of the project consists of the construction of a new State of Texas Dept. of Public Safety Area Office Building.  The office building footprint is approximately 15,900 S.F. on one floor with site development and parking as described and indicated in the contract documents:  1) Demolition, removal, and disposal of existing site trees, roots, shrubs, vegetation, sus-surface obstructions and excess soils that are in conflict with the planned improvements.  2) Construction of the project in its entirety as described and indicated in the Contract Documents.
Notes:
Owner:                    Texas Facilities Commission, Austin
Arch/Eng:             Negrete & Kolar Archtects, Austin 512/474-6526
General Contractors:

 